Question 310
A rail platform installation misses an approved scope tolerance and a project manager proposes quietly modifying the existing stage plan after escalation. Which diagnosis most accurately explains the gap in control?
Explanation
Correct Answer
The important PRINCE2 distinction is that a forecast tolerance breach moves decisions beyond the manager's delegation; an exception plan supplies the basis for a revised authorized commitment. That reasoning makes the targeted action appropriate: prepare an exception plan when requested by the appropriate authority to replace the affected plan following an authorized exception decision. The described project conditions show why the distinction matters: A rail platform installation misses an approved scope tolerance and a project manager proposes quietly modifying the existing stage plan after escalation.
Incorrect Answers
Recognize negative consequences describes a different management issue. The relevant cause instead is that a forecast tolerance breach moves decisions beyond the manager's delegation; an exception plan supplies the basis for a revised authorized commitment.
Product register and configuration identification describes a different management issue. The relevant cause instead is that a forecast tolerance breach moves decisions beyond the manager's delegation; an exception plan supplies the basis for a revised authorized commitment.
Keep the issue register and report aligned describes a different management issue. The relevant cause instead is that a forecast tolerance breach moves decisions beyond the manager's delegation; an exception plan supplies the basis for a revised authorized commitment.