Question 410
An e-learning project assigns a junior technician to perform a cybersecurity mitigation but has no accountable person monitoring the overall risk exposure. Which diagnosis most accurately explains the gap in control?
Explanation
Correct Answer
The important PRINCE2 distinction is that the risk owner is accountable for managing exposure, whereas actionees carry out agreed responses; one label cannot replace both responsibilities. That reasoning makes the targeted action appropriate: name an accountable risk owner and specific risk actionees with deliverables, deadlines and escalation arrangements. The described project conditions show why the distinction matters: An e-learning project assigns a junior technician to perform a cybersecurity mitigation but has no accountable person monitoring the overall risk exposure.
Incorrect Answers
Use time-sensitive early warning indicators describes a different management issue. The relevant cause instead is that the risk owner is accountable for managing exposure, whereas actionees carry out agreed responses; one label cannot replace both responsibilities.
Manage a risk that threatens tolerance describes a different management issue. The relevant cause instead is that the risk owner is accountable for managing exposure, whereas actionees carry out agreed responses; one label cannot replace both responsibilities.
Use a risk budget for uncertainty describes a different management issue. The relevant cause instead is that the risk owner is accountable for managing exposure, whereas actionees carry out agreed responses; one label cannot replace both responsibilities.