Question 430
A transport data project models a likely regulatory delay exceeding overall project time tolerance but reports only that the risk register has been updated. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that a risk can cause a forecast exception before an issue actually happens; recording the risk alone does not authorize exceeding delegated constraints. That reasoning makes the targeted action appropriate: escalate a forecast tolerance threat to the appropriate level and present response options while continuing proportionate risk treatment. The described project conditions show why the distinction matters: A transport data project models a likely regulatory delay exceeding overall project time tolerance but reports only that the risk register has been updated.
Incorrect Answers
Tailor planning for iterative delivery describes a different management issue. The relevant cause instead is that a risk can cause a forecast exception before an issue actually happens; recording the risk alone does not authorize exceeding delegated constraints.
Resolve failed quality criteria before acceptance describes a different management issue. The relevant cause instead is that a risk can cause a forecast exception before an issue actually happens; recording the risk alone does not authorize exceeding delegated constraints.
Maintain the quality register describes a different management issue. The relevant cause instead is that a risk can cause a forecast exception before an issue actually happens; recording the risk alone does not authorize exceeding delegated constraints.