Question 450
A regional tax filing portal meets its agreed specification, but the customer now wants another language interface not in the product baseline. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that a change to an agreed baseline and a failure to meet that baseline are different issues; misclassification distorts cost, authority and quality decisions. That reasoning makes the targeted action appropriate: classify and assess the issue correctly as a request for change, off-specification or problem before choosing its management route. The described project conditions show why the distinction matters: A regional tax filing portal meets its agreed specification, but the customer now wants another language interface not in the product baseline.
Incorrect Answers
Apply delegated change authority describes a different management issue. The relevant cause instead is that a change to an agreed baseline and a failure to meet that baseline are different issues; misclassification distorts cost, authority and quality decisions.
Assess impact before approving a change describes a different management issue. The relevant cause instead is that a change to an agreed baseline and a failure to meet that baseline are different issues; misclassification distorts cost, authority and quality decisions.
Keep the issue register and report aligned describes a different management issue. The relevant cause instead is that a change to an agreed baseline and a failure to meet that baseline are different issues; misclassification distorts cost, authority and quality decisions.