Question 470
A team manager approves an unbudgeted change to critical safety requirements because the supplier says delivery will be faster. Which diagnosis most accurately explains the gap in control?
Explanation
Correct Answer
The important PRINCE2 distinction is that delegated authority enables proportionate decisions but cannot legitimize changes outside the allocated budget, scope or safety conditions. That reasoning makes the targeted action appropriate: use the documented change authority within its delegated scope, escalating only decisions beyond the agreed constraints. The described project conditions show why the distinction matters: A team manager approves an unbudgeted change to critical safety requirements because the supplier says delivery will be faster.
Incorrect Answers
Project support and administrative control describes a different management issue. The relevant cause instead is that delegated authority enables proportionate decisions but cannot legitimize changes outside the allocated budget, scope or safety conditions.
Identify threats and opportunities explicitly describes a different management issue. The relevant cause instead is that delegated authority enables proportionate decisions but cannot legitimize changes outside the allocated budget, scope or safety conditions.
Choose an exception plan after escalation describes a different management issue. The relevant cause instead is that delegated authority enables proportionate decisions but cannot legitimize changes outside the allocated budget, scope or safety conditions.