Question 490
A regional hospital project has the same unresolved integration issue described differently in three emails, a risk log and a board slide. What underlying management principle most directly explains the concern?
Explanation
Correct Answer
The important PRINCE2 distinction is that the issue register supports tracking, while an issue report documents focused analysis and recommendations; neither should be replaced by scattered correspondence. That reasoning makes the targeted action appropriate: maintain a controlled issue register and prepare issue reports for significant matters requiring analysis or authority decisions. The described project conditions show why the distinction matters: A regional hospital project has the same unresolved integration issue described differently in three emails, a risk log and a board slide.
Incorrect Answers
Manage cumulative changes and change budget describes a different management issue. The relevant cause instead is that the issue register supports tracking, while an issue report documents focused analysis and recommendations; neither should be replaced by scattered correspondence.
Control an off-specification describes a different management issue. The relevant cause instead is that the issue register supports tracking, while an issue report documents focused analysis and recommendations; neither should be replaced by scattered correspondence.
Distinguish request for change from defect describes a different management issue. The relevant cause instead is that the issue register supports tracking, while an issue report documents focused analysis and recommendations; neither should be replaced by scattered correspondence.