Question 650
A university data project has prepared its PID and detailed controls but its manager starts full development before the board approves the project. What underlying management principle most directly explains the concern?
Explanation
Correct Answer
The important PRINCE2 distinction is that approval of initiation provides authority to prepare baselines, not automatic authority for all project implementation. That reasoning makes the targeted action appropriate: submit a sufficiently complete PID and refined business case to the board for explicit authorization to deliver the project. The described project conditions show why the distinction matters: A university data project has prepared its PID and detailed controls but its manager starts full development before the board approves the project.
Incorrect Answers
Create a defensible exception plan describes a different management issue. The relevant cause instead is that approval of initiation provides authority to prepare baselines, not automatic authority for all project implementation.
Monitor work-package progress describes a different management issue. The relevant cause instead is that approval of initiation provides authority to prepare baselines, not automatic authority for all project implementation.
Evaluate performance and lessons describes a different management issue. Here the observed concern is: A university data project has prepared its PID and detailed controls but its manager starts full development before the board approves the project. The relevant cause instead is that approval of initiation provides authority to prepare baselines, not automatic authority for all project implementation.