Question 670
A regional health system team manager reports optimistic percent-complete figures without product evidence or a forecast of remaining work. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that the project manager needs timely information from teams to control stage delivery and correct deviations before tolerances are breached. That reasoning makes the targeted action appropriate: obtain agreed checkpoint reports and assess actual and forecast work-package progress against the current authorized stage plan. The described project conditions show why the distinction matters: A regional health system team manager reports optimistic percent-complete figures without product evidence or a forecast of remaining work.
Incorrect Answers
Refine business case and project plan describes a different management issue. The relevant cause instead is that the project manager needs timely information from teams to control stage delivery and correct deviations before tolerances are breached.
Accept a defined work package describes a different management issue. The relevant cause instead is that the project manager needs timely information from teams to control stage delivery and correct deviations before tolerances are breached.
Distinguish planned and premature closure describes a different management issue. The relevant cause instead is that the project manager needs timely information from teams to control stage delivery and correct deviations before tolerances are breached.