Question 690
A city water-meter project sends a stream of individual engineer notes to its board but no clear stage forecast or decisions required. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that highlight reports summarize authorized stage performance; exception reports seek a higher-level decision once delegated limits will be exceeded. That reasoning makes the targeted action appropriate: produce proportionate highlight reports during normal control and separate exception reporting when a forecast exceeds stage tolerance. The described project conditions show why the distinction matters: A city water-meter project sends a stream of individual engineer notes to its board but no clear stage forecast or decisions required.
Incorrect Answers
Monitor work-package progress describes a different management issue. The relevant cause instead is that highlight reports summarize authorized stage performance; exception reports seek a higher-level decision once delegated limits will be exceeded.
Take corrective action within authority describes a different management issue. The relevant cause instead is that highlight reports summarize authorized stage performance; exception reports seek a higher-level decision once delegated limits will be exceeded.
Authorize work packages describes a different management issue. The relevant cause instead is that highlight reports summarize authorized stage performance; exception reports seek a higher-level decision once delegated limits will be exceeded.