Question 680
A city planning system has available testing resources that could recover a work-package slippage, but the manager assumes only the board can rearrange tasks. Which recurring review would keep this control effective as the project changes?
Explanation
Correct Answer
Monitor the effects of corrective action and escalate promptly if updated forecasts still show an exception. It is appropriate because controlling a stage includes local management action without escalating every minor variance; escalation is required only when delegated limits are forecast to be exceeded. The recurring failure risk is illustrated by: A city planning system has available testing resources that could recover a work-package slippage, but the manager assumes only the board can rearrange tasks.
Incorrect Answers
This repeating check is mainly concerned with appoint accountable leadership before initiation, not with the recurring weakness described here: A city planning system has available testing resources that could recover a work-package slippage, but the manager assumes only the board can rearrange tasks. The useful ongoing safeguard in this situation is to monitor the effects of corrective action and escalate promptly if updated forecasts still show an exception.
This repeating check is mainly concerned with refine business case and project plan, not with the recurring weakness described here: A city planning system has available testing resources that could recover a work-package slippage, but the manager assumes only the board can rearrange tasks. The useful ongoing safeguard in this situation is to monitor the effects of corrective action and escalate promptly if updated forecasts still show an exception.
This repeating check is mainly concerned with monitor work-package progress, not with the recurring weakness described here: A city planning system has available testing resources that could recover a work-package slippage, but the manager assumes only the board can rearrange tasks. The useful ongoing safeguard in this situation is to monitor the effects of corrective action and escalate promptly if updated forecasts still show an exception.