McAfee Secure

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

PRINCE2 PRINCE2 7 Practitioner Questions & Answers

Study with Up-To-Date REAL Exam Questions and Answers from the ACTUAL Test

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 79

Question 780

A smart-building project delivers its monitoring dashboard but leaves the facilities team without support ownership or incident response procedures. Which recurring review would keep this control effective as the project changes?

  1. Agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.
  2. Resolve ambiguity before execution and use agreed package change procedures if dependencies or acceptance expectations shift.
  3. Review the source of lessons and preliminary assumptions before consuming initiation resources or expanding the project team.
  4. Maintain a clear early-closure route and avoid treating cancellation as permission to abandon governance, records or handover duties.

Explanation

Correct Answer

A:

Agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization. It is appropriate because project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk. The recurring failure risk is illustrated by: A smart-building project delivers its monitoring dashboard but leaves the facilities team without support ownership or incident response procedures.

Incorrect Answers

B:

This repeating check is mainly concerned with accept a defined work package, not with the recurring weakness described here: A smart-building project delivers its monitoring dashboard but leaves the facilities team without support ownership or incident response procedures. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

C:

This repeating check is mainly concerned with use lessons and outline business case, not with the recurring weakness described here: A smart-building project delivers its monitoring dashboard but leaves the facilities team without support ownership or incident response procedures. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

D:

This repeating check is mainly concerned with distinguish planned and premature closure, not with the recurring weakness described here: A smart-building project delivers its monitoring dashboard but leaves the facilities team without support ownership or incident response procedures. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

Question 781

A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. What should the responsible project role do next to restore effective control?

  1. Prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking.
  2. Verify that the project's required products meet agreed acceptance criteria and obtain formal acceptance from the appropriate authority.
  3. Have the board review closure evidence and authorize formal project closure only when acceptance and necessary follow-on duties are understood.
  4. Update the business case and benefits forecasts using the completed stage evidence before recommending continuation.

Explanation

Correct Answer

A:

The situation calls for this intervention because project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk. Prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking. The response can be checked against delivery evidence: operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules.

Incorrect Answers

B:

Confirm acceptance of final products concerns a different project control. Here, prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking. The reason is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

C:

Authorize a controlled closure concerns a different project control. Here, prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking. The reason is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

D:

Refresh the business case concerns a different project control. Here, prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking. The reason is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

Question 782

A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. Why is the proposed way of working inappropriate in this situation?

  1. Stage control requires active issue and risk management; informal observations must become governed decisions when they affect products or constraints.
  2. Team-level execution must achieve accepted quality expectations, not merely produce activity outputs or shift all checking to the project manager.
  3. PRINCE2 closure confirms product acceptance; stopping technical work or exhausting the stage budget is not equivalent to meeting the agreed requirements.
  4. Project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

Explanation

Correct Answer

D:

The important PRINCE2 distinction is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk. That reasoning makes the targeted action appropriate: prepare handover and follow-on action recommendations with clear owners for operations, outstanding work, support and benefits tracking. The described project conditions show why the distinction matters: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

Incorrect Answers

A:

Manage issues and risks in the stage describes a different management issue. The relevant cause instead is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

B:

Execute and assure products describes a different management issue. The relevant cause instead is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

C:

Confirm acceptance of final products describes a different management issue. The relevant cause instead is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk.

Question 783

A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. What project record best demonstrates effective handling of the reported issue?

  1. Operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules.
  2. The PID shows practical approaches, owners, decision routes and reporting arrangements linked to specific products and risks.
  3. The board receives a next-stage plan with agreed products, dependencies, budget, schedule and tolerance assumptions before authorization.
  4. The executive and project manager are named with roles agreed, and the board has enough preliminary information to consider initiation.

Explanation

Correct Answer

A:

Operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules. The controlling requirement is that project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk. The evidence directly addresses the situation: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

Incorrect Answers

B:

Evidence about establish management approaches before execution would not show that this problem was resolved. The present project needs to prove that operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules. The specific condition to test arises from: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

C:

Evidence about plan the next authorized stage would not show that this problem was resolved. The present project needs to prove that operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules. The specific condition to test arises from: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

D:

Evidence about appoint accountable leadership before initiation would not show that this problem was resolved. The present project needs to prove that operational owners acknowledge products, support arrangements, open actions, contract obligations and post-project benefit review schedules. The specific condition to test arises from: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

Question 784

A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. Which ongoing control would best prevent this failure from recurring?

  1. Keep reporting consistent with package tolerances and communicate forecast breaches before the scheduled end date.
  2. Adjust monitoring intensity and corrective action when emerging evidence suggests the package may miss its commitment.
  3. Agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.
  4. Use startup checks to confirm decision authority and management ownership before authorizing detailed project initiation.

Explanation

Correct Answer

C:

Agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization. It is appropriate because project closure transfers responsibility to receiving operations; leaving residual obligations with a disbanding team creates uncontrolled risk. The recurring failure risk is illustrated by: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner.

Incorrect Answers

A:

This repeating check is mainly concerned with send checkpoint information, not with the recurring weakness described here: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

B:

This repeating check is mainly concerned with monitor work-package progress, not with the recurring weakness described here: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

D:

This repeating check is mainly concerned with appoint accountable leadership before initiation, not with the recurring weakness described here: A digital grants project closes while unresolved minor defects, contracts and maintenance commitments have no receiving owner. The useful ongoing safeguard in this situation is to agree transition responsibilities before closure and confirm that unresolved actions remain tracked by the receiving organization.

Question 785

A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. What should the responsible project role do next to restore effective control?

  1. Obtain agreed checkpoint reports and assess actual and forecast work-package progress against the current authorized stage plan.
  2. Prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure.
  3. Authorize and agree work packages with clear deliverables, quality criteria, tolerances, dependencies and reporting arrangements before execution.
  4. Prepare a realistic next-stage plan with products, estimates, constraints, risks and proposed tolerances for board consideration.

Explanation

Correct Answer

B:

This response is justified because a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. Prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The response can be checked against delivery evidence: the end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects.

Incorrect Answers

A:

Monitor work-package progress concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

C:

Authorize work packages concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

D:

Plan the next authorized stage concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

Question 786

A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. Why is the proposed way of working inappropriate in this situation?

  1. Controlling a stage includes local management action without escalating every minor variance; escalation is required only when delegated limits are forecast to be exceeded.
  2. A closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.
  3. An exception plan replaces the relevant approved plan only after appropriate authority reviews the forecast breach and proposed course of action.
  4. Starting up a project checks whether there is a worthwhile, viable basis for initiation before significant delivery resources are committed.

Explanation

Correct Answer

B:

The important PRINCE2 distinction is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. That reasoning makes the targeted action appropriate: prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The described project conditions show why the distinction matters: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

Incorrect Answers

A:

Take corrective action within authority describes a different management issue. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

C:

Create a defensible exception plan describes a different management issue. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

D:

Appoint accountable leadership before initiation describes a different management issue. Here the observed concern is: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

Question 787

A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. What project record best demonstrates effective handling of the reported issue?

  1. The team manager accepts the authorized work package and the project manager can trace its products and reporting to stage commitments.
  2. The project brief records the recommended route and its key assumptions, enabling the board to assess the feasibility of starting.
  3. The decision record links the exception report, revised plan, tolerances, changed business case and board authorization of the new baseline.
  4. The end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects.

Explanation

Correct Answer

D:

The end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects. The controlling requirement is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. The evidence directly addresses the situation: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

Incorrect Answers

A:

Evidence about authorize work packages would not show that this problem was resolved. The present project needs to prove that the end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects. The specific condition to test arises from: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

B:

Evidence about define the initial project approach would not show that this problem was resolved. The present project needs to prove that the end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects. The specific condition to test arises from: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

C:

Evidence about create a defensible exception plan would not show that this problem was resolved. The present project needs to prove that the end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects. The specific condition to test arises from: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

Question 788

A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. Which ongoing control would best prevent this failure from recurring?

  1. Capture lessons throughout execution and confirm relevant organizational recipients receive them at closure.
  2. Control PID changes and maintain traceable version history so later stages use authorized assumptions.
  3. Use the directing process to keep strategic decision rights distinct from the project manager's preparation and delivery work.
  4. Require fresh authorization at stage boundaries using current forecasts, not automatic continuation of an obsolete budget.

Explanation

Correct Answer

A:

Capture lessons throughout execution and confirm relevant organizational recipients receive them at closure. It is appropriate because a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. The recurring failure risk is illustrated by: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline.

Incorrect Answers

B:

This repeating check is mainly concerned with create a coherent pid baseline, not with the recurring weakness described here: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. The useful ongoing safeguard in this situation is to capture lessons throughout execution and confirm relevant organizational recipients receive them at closure.

C:

This repeating check is mainly concerned with authorize initiation separately from full delivery, not with the recurring weakness described here: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. The useful ongoing safeguard in this situation is to capture lessons throughout execution and confirm relevant organizational recipients receive them at closure.

D:

This repeating check is mainly concerned with authorize project and stages, not with the recurring weakness described here: A public transport app team reports only final feature counts and never compares cost, time, quality or benefits forecast with the approved project baseline. The useful ongoing safeguard in this situation is to capture lessons throughout execution and confirm relevant organizational recipients receive them at closure.

Question 789

A municipal water metering rollout finishes successfully but records no lessons about repeated supplier handoff problems that future projects could use. Which action is the most proportionate response to the stated problem?

  1. Have the team manager review and formally accept the work package with products, dependencies, quality controls and reporting obligations understood.
  2. Gather relevant lessons and prepare an outline business case and project brief so an informed authorization-to-initiate decision is possible.
  3. Prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure.
  4. Produce the work-package products using approved technical methods, carry out required quality controls and keep evidence linked to each item.

Explanation

Correct Answer

C:

The situation calls for this intervention because a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. Prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The response can be checked against delivery evidence: the end project and lessons reports document product acceptance, variances, value assumptions, residual risks and actionable learning for future projects.

Incorrect Answers

A:

Accept a defined work package concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

B:

Use lessons and outline business case concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

D:

Execute and assure products concerns a different project control. Here, prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The reason is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

Question 790

A municipal water metering rollout finishes successfully but records no lessons about repeated supplier handoff problems that future projects could use. Which diagnosis most accurately explains the gap in control?

  1. A closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.
  2. Controlling a stage turns the stage plan into bounded delegated work; an informal task list cannot establish reliable delivery accountability.
  3. The startup process should provide a controlled basis for the board to approve initiation so detailed baselines can be established.
  4. Starting up a project checks whether there is a worthwhile, viable basis for initiation before significant delivery resources are committed.

Explanation

Correct Answer

A:

The important PRINCE2 distinction is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed. That reasoning makes the targeted action appropriate: prepare a final evaluation of actual performance against the approved plan and communicate transferable lessons before recommending closure. The described project conditions show why the distinction matters: A municipal water metering rollout finishes successfully but records no lessons about repeated supplier handoff problems that future projects could use.

Incorrect Answers

B:

Authorize work packages describes a different management issue. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

C:

Plan the initiation stage describes a different management issue. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

D:

Appoint accountable leadership before initiation describes a different management issue. The relevant cause instead is that a closing process should explain delivery performance and learning, not simply assert that all scheduled tasks were completed.

PRINCE2 7 Practitioner Practice Tests