Question 770
A city food inspection platform reaches the last sprint but the regulatory customer has not accepted the reporting outputs against agreed criteria. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that pRINCE2 closure confirms product acceptance; stopping technical work or exhausting the stage budget is not equivalent to meeting the agreed requirements. That reasoning makes the targeted action appropriate: verify that the project's required products meet agreed acceptance criteria and obtain formal acceptance from the appropriate authority. The described project conditions show why the distinction matters: A city food inspection platform reaches the last sprint but the regulatory customer has not accepted the reporting outputs against agreed criteria.
Incorrect Answers
Evaluate performance and lessons describes a different management issue. The relevant cause instead is that pRINCE2 closure confirms product acceptance; stopping technical work or exhausting the stage budget is not equivalent to meeting the agreed requirements.
Distinguish planned and premature closure describes a different management issue. Here the observed concern is: A city food inspection platform reaches the last sprint but the regulatory customer has not accepted the reporting outputs against agreed criteria. The relevant cause instead is that pRINCE2 closure confirms product acceptance; stopping technical work or exhausting the stage budget is not equivalent to meeting the agreed requirements.
Arrange ongoing support and follow-on actions describes a different management issue. The relevant cause instead is that pRINCE2 closure confirms product acceptance; stopping technical work or exhausting the stage budget is not equivalent to meeting the agreed requirements.