Question 750
A public energy data project finds adoption lower than forecast but seeks continuation funding without reconsidering benefit assumptions. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that each major funding decision should consider whether the project remains viable, desirable and achievable in light of current data. That reasoning makes the targeted action appropriate: update the business case and benefits forecasts using the completed stage evidence before recommending continuation. The described project conditions show why the distinction matters: A public energy data project finds adoption lower than forecast but seeks continuation funding without reconsidering benefit assumptions.
Incorrect Answers
Use lessons and outline business case describes a different management issue. The relevant cause instead is that each major funding decision should consider whether the project remains viable, desirable and achievable in light of current data.
Refine business case and project plan describes a different management issue. The relevant cause instead is that each major funding decision should consider whether the project remains viable, desirable and achievable in light of current data.
Manage issues and risks in the stage describes a different management issue. The relevant cause instead is that each major funding decision should consider whether the project remains viable, desirable and achievable in light of current data.