Question 740
A regional records programme closes its pilot and immediately assigns national rollout work without a stage plan for suppliers, locations or acceptance. Which ongoing practice would best sustain effective control in this situation?
Explanation
Correct Answer
Keep near-term stage plans aligned with the project plan and revise forecasts when dependencies or resource availability change. It is appropriate because the project board authorizes a bounded near-term stage based on current evidence, not a vague promise derived from an obsolete overall plan. The recurring failure risk is illustrated by: A regional records programme closes its pilot and immediately assigns national rollout work without a stage plan for suppliers, locations or acceptance.
Incorrect Answers
This repeating check is mainly concerned with refresh the business case, not with the recurring weakness described here: A regional records programme closes its pilot and immediately assigns national rollout work without a stage plan for suppliers, locations or acceptance. The useful ongoing safeguard in this situation is to keep near-term stage plans aligned with the project plan and revise forecasts when dependencies or resource availability change.
This repeating check is mainly concerned with request explicit next-stage authorization, not with the recurring weakness described here: A regional records programme closes its pilot and immediately assigns national rollout work without a stage plan for suppliers, locations or acceptance. The useful ongoing safeguard in this situation is to keep near-term stage plans aligned with the project plan and revise forecasts when dependencies or resource availability change.
This repeating check is mainly concerned with create a defensible exception plan, not with the recurring weakness described here: A regional records programme closes its pilot and immediately assigns national rollout work without a stage plan for suppliers, locations or acceptance. The useful ongoing safeguard in this situation is to keep near-term stage plans aligned with the project plan and revise forecasts when dependencies or resource availability change.