Question 330
In a target-architecture development workshop for fictional Sable Peak Services, reviewers observe: A bank assumes all existing servers will support the target application requirements without an infrastructure baseline analysis. What acceptance evidence would demonstrate an effective architecture correction?
Explanation
Correct Answer
The technology design accounts for platforms, networks, and infrastructure gaps that affect target workloads. That result is the most direct evidence that the proposed action worked: Use Phase D to develop baseline and target Technology Architecture aligned to business and information systems requirements. It confirms the underlying distinction: Phase D develops the technology foundation needed by the target business and information systems architectures. Applied here, the relevant facts are: A bank assumes all existing servers will support the target application requirements without an infrastructure baseline analysis.
Incorrect Answers
“Teams understand the role of each phase and can trace changing requirements across phases” could occur while the stated failure remains unresolved. It tests: That result is the most direct evidence that the proposed action worked: Identify the applicable ADM phase purposes and maintain requirements throughout the iterative architecture cycle. The required validation instead is “The technology design accounts for platforms, networks, and infrastructure gaps that affect target workloads”, because that result is the most direct evidence that the proposed action worked: Use Phase D to develop baseline and target Technology Architecture aligned to business and information systems requirements.
This checks a different technical dependency: That result is the most direct evidence that the proposed action worked: Govern implementation using architecture conformance evidence and agreed contracts in Phase G. The case requires proof of “The technology design accounts for platforms, networks, and infrastructure gaps that affect target workloads”, which establishes the relevant condition: That result is the most direct evidence that the proposed action worked: Use Phase D to develop baseline and target Technology Architecture aligned to business and information systems requirements.
“Sponsors can review plausible solution groupings and interim states before detailed migration sequencing” could occur while the stated failure remains unresolved. It tests: Sponsors can review plausible solution groupings and interim states before detailed migration sequencing. The required validation instead is “The technology design accounts for platforms, networks, and infrastructure gaps that affect target workloads”, because that result is the most direct evidence that the proposed action worked: Use Phase D to develop baseline and target Technology Architecture aligned to business and information systems requirements.