Question 550
At fictional Copperfield University, during an architecture phase review, stakeholders identify: A new e-commerce initiative lists technology components but has no stakeholder-approved business outcome or architecture work boundary. Which next architecture action best addresses the specific situation?
Explanation
Correct Answer
Secure shared high-level Architecture Vision and Statement of Architecture Work in Phase A. The issue requires this response because phase a provides commitment to the architecture vision before detailed target modeling. Confirmation would be: The sponsor agrees the purpose, intended benefits, and scope of architecture development. Applied here, the relevant facts are: A new e-commerce initiative lists technology components but has no stakeholder-approved business outcome or architecture work boundary.
Incorrect Answers
“In Phase E, group work packages, identify potential Transition Architectures, and build an initial Architecture Roadmap” can be suitable where phase E identifies implementation opportunities and initial transition approaches rather than executing the migration. It does not resolve this question’s narrower failure, which follows: Phase A provides commitment to the architecture vision before detailed target modeling. The relevant action is “Secure shared high-level Architecture Vision and Statement of Architecture Work in Phase A”.
The alternative focuses on the technical control described by: Opportunities and solutions turns architectural gaps into candidate implementation building blocks and work packages. The present requirement is governed by: Phase A provides commitment to the architecture vision before detailed target modeling. Apply “Secure shared high-level Architecture Vision and Statement of Architecture Work in Phase A” to address that particular cause.
“Establish explicit information flow and traceability between ADM phase outputs, requirements, and downstream decisions” can be suitable where the ADM relies on iterative information exchange across phases rather than independent linear work packets. It does not resolve this question’s narrower failure, which follows: Phase A provides commitment to the architecture vision before detailed target modeling. The relevant action is “Secure shared high-level Architecture Vision and Statement of Architecture Work in Phase A”.