  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Training Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Training Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 22

Question 210

In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Include committed costs and forecasts in the cost management baseline review.
  2. Define measurable quality acceptance criteria and a method of inspection.
  3. Register the vendor dependency with impact, response owner, and contingency action.
  4. Estimate inspection resource demand and confirm scarce inspector capacity on critical dates.

Explanation

Correct Answer

D:

This directly addresses the case's governing problem: Estimate inspection resource demand and confirm scarce inspector capacity on critical dates. The key reason is that resource availability is a real feasibility constraint for schedule commitments. A suitable completion check is: The resource schedule includes qualified inspector bookings and realistic sequencing.

Incorrect Answers

A:

“Include committed costs and forecasts in the cost management baseline review” responds to another technical or business failure: In a fictional CAPM project situation, a school renovation's budget tracks contractor invoices but omits committed purchase orders. That source case depends on: Ignoring commitments makes the remaining funding appear healthier than reality. The present issue is: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. The more direct action is “Estimate inspection resource demand and confirm scarce inspector capacity on critical dates” because resource availability is a real feasibility constraint for schedule commitments.

B:

“Define measurable quality acceptance criteria and a method of inspection” responds to another technical or business failure: In a fictional CAPM project situation, a food-packaging launch has no criteria for rejecting defective seal strength. That source case depends on: Quality must be specified and verified, not inferred from completion alone. The present issue is: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. The more direct action is “Estimate inspection resource demand and confirm scarce inspector capacity on critical dates” because resource availability is a real feasibility constraint for schedule commitments.

C:

“Register the vendor dependency with impact, response owner, and contingency action” responds to another technical or business failure: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. That source case depends on: Planning for uncertainty is more effective before the vendor fails. The present issue is: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. The more direct action is “Estimate inspection resource demand and confirm scarce inspector capacity on critical dates” because resource availability is a real feasibility constraint for schedule commitments.

Question 211

In a fictional CAPM project situation, an insurance claims modernization team asks the IT lead to define business exceptions without consulting the actual claims process owner. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Review decision rights when product and process ownership change.
  2. Refresh the stakeholder register after workflow changes.
  3. Use regular external-user feedback and accessibility review.
  4. Keep process-owner signoff in requirements and change governance.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Keep process-owner signoff in requirements and change governance. It follows the targeted action (have the process owner approve exception rules while IT translates them into system behavior.) and provides a way to catch recurrence. The underlying principle is: IT delivery expertise does not replace business-policy accountability.

Incorrect Answers

A:

“Review decision rights when product and process ownership change” addresses recurrence of another problem: In a fictional CAPM project situation, a subscription platform is changing checkout rules but no one can say who is accountable for final business priority. That problem depends on: This ongoing practice maintains the improvement: Review decision rights when product and process ownership change. The recurring risk here is: In a fictional CAPM project situation, an insurance claims modernization team asks the IT lead to define business exceptions without consulting the actual claims process owner. The more targeted safeguard is “Keep process-owner signoff in requirements and change governance” because this ongoing practice maintains the improvement: Keep process-owner signoff in requirements and change governance.

B:

“Refresh the stakeholder register after workflow changes” addresses recurrence of another problem: In a fictional CAPM project situation, a municipal licensing redesign excludes frontline clerks even though their tasks will change. That problem depends on: This ongoing practice maintains the improvement: Refresh the stakeholder register after workflow changes. The recurring risk here is: In a fictional CAPM project situation, an insurance claims modernization team asks the IT lead to define business exceptions without consulting the actual claims process owner. The more targeted safeguard is “Keep process-owner signoff in requirements and change governance” because this ongoing practice maintains the improvement: Keep process-owner signoff in requirements and change governance.

C:

“Use regular external-user feedback and accessibility review” addresses recurrence of another problem: In a fictional CAPM project situation, a public payment portal team collects only internal views and ignores external taxpayers. That problem depends on: This ongoing practice maintains the improvement: Use regular external-user feedback and accessibility review. The recurring risk here is: In a fictional CAPM project situation, an insurance claims modernization team asks the IT lead to define business exceptions without consulting the actual claims process owner. The more targeted safeguard is “Keep process-owner signoff in requirements and change governance” because this ongoing practice maintains the improvement: Keep process-owner signoff in requirements and change governance.

Question 212

In a fictional CAPM project situation, a software team's daily coordination meeting has become a detailed design debate among two engineers. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Conduct a moderated focus group with representative visitors and open questions.
  2. Facilitate an initial nonjudgmental ideation phase followed by clear evaluation criteria.
  3. Take the deep technical discussion offline and keep the standup focused on progress and impediments.
  4. Use confidential interviews before any group workshop to protect candid input.

Explanation

Correct Answer

C:

This directly addresses the case's governing problem: Take the deep technical discussion offline and keep the standup focused on progress and impediments. The key reason is that short coordination meetings should not be consumed by unrelated problem-solving. A suitable completion check is: The standup surfaces blockers and the follow-up design session resolves the dispute.

Incorrect Answers

A:

“Conduct a moderated focus group with representative visitors and open questions” responds to another technical or business failure: In a fictional CAPM project situation, a museum wants reactions to a proposed visitor experience before the requirements are finalized. That source case depends on: Focus groups explore perceptions; they are not a statistically representative vote. The present issue is: In a fictional CAPM project situation, a software team's daily coordination meeting has become a detailed design debate among two engineers. The more direct action is “Take the deep technical discussion offline and keep the standup focused on progress and impediments” because short coordination meetings should not be consumed by unrelated problem-solving.

B:

“Facilitate an initial nonjudgmental ideation phase followed by clear evaluation criteria” responds to another technical or business failure: In a fictional CAPM project situation, a team brainstorms solutions for recurring late shipments while one manager immediately rejects every suggestion. That source case depends on: Premature criticism suppresses alternatives and weakens group problem solving. The present issue is: In a fictional CAPM project situation, a software team's daily coordination meeting has become a detailed design debate among two engineers. The more direct action is “Take the deep technical discussion offline and keep the standup focused on progress and impediments” because short coordination meetings should not be consumed by unrelated problem-solving.

D:

“Use confidential interviews before any group workshop to protect candid input” responds to another technical or business failure: In a fictional CAPM project situation, a team uses a large open workshop to gather private feedback about conflicts with a supervisor. That source case depends on: Sensitive power dynamics can suppress honest responses in an open group. The present issue is: In a fictional CAPM project situation, a software team's daily coordination meeting has become a detailed design debate among two engineers. The more direct action is “Take the deep technical discussion offline and keep the standup focused on progress and impediments” because short coordination meetings should not be consumed by unrelated problem-solving.

Question 213

In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. Which underlying project-management principle best explains the appropriate response?

  1. Critical path duration follows the longest start-to-finish dependent sequence.
  2. The longest dependent path sets the earliest possible finish when resources are unconstrained.
  3. Earned value below planned value indicates less budgeted work achieved than scheduled.
  4. Actual cost exceeds the budgeted value of work performed, indicating overrun.

Explanation

Correct Answer

B:

The case turns on this distinction: The longest dependent path sets the earliest possible finish when resources are unconstrained. Consequently, the targeted action is: Schedule using the 12-day A-B-D critical path and protect its dependencies. This reasoning can be checked against: Network calculations show A-B-D totals 12 days and A-C-D totals 9 days.

Incorrect Answers

A:

“Critical path duration follows the longest start-to-finish dependent sequence” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a port upgrade has branch X 5d plus Y 4d and branch X 5d plus Z 7d, joining at final acceptance T 2d. There the technical reason is: Critical path duration follows the longest start-to-finish dependent sequence. In this question, the reported issue is: In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. The controlling principle is instead: The longest dependent path sets the earliest possible finish when resources are unconstrained.

C:

“Earned value below planned value indicates less budgeted work achieved than scheduled” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. There the technical reason is: Earned value below planned value indicates less budgeted work achieved than scheduled. In this question, the reported issue is: In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. The controlling principle is instead: The longest dependent path sets the earliest possible finish when resources are unconstrained.

D:

“Actual cost exceeds the budgeted value of work performed, indicating overrun” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. There the technical reason is: Actual cost exceeds the budgeted value of work performed, indicating overrun. In this question, the reported issue is: In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. The controlling principle is instead: The longest dependent path sets the earliest possible finish when resources are unconstrained.

Question 214

In a fictional CAPM project situation, a health network is coordinating a shared electronic-record program containing several interdependent hospital migrations. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Use portfolio selection to evaluate the unrelated initiatives against strategic value and capacity.
  2. Manage the related hospital migrations as a coordinated program rather than unrelated portfolio entries.
  3. Use a predictive approach with an agreed requirements baseline and formal changes.
  4. Use iterative adaptive delivery with early increments and frequent customer feedback.

Explanation

Correct Answer

B:

This directly addresses the case's governing problem: Manage the related hospital migrations as a coordinated program rather than unrelated portfolio entries. The key reason is that a program coordinates related projects to realize benefits unavailable through isolated management. A suitable completion check is: Joint dependency and benefit reports show hospital migrations managed toward one combined capability.

Incorrect Answers

A:

“Use portfolio selection to evaluate the unrelated initiatives against strategic value and capacity” responds to another technical or business failure: In a fictional CAPM project situation, a retail board is comparing an unrelated warehouse expansion, loyalty application, and energy-efficiency upgrade to fund strategic priorities. That source case depends on: A portfolio groups investments for strategic management even when individual projects are unrelated. The present issue is: In a fictional CAPM project situation, a health network is coordinating a shared electronic-record program containing several interdependent hospital migrations. The more direct action is “Manage the related hospital migrations as a coordinated program rather than unrelated portfolio entries” because a program coordinates related projects to realize benefits unavailable through isolated management.

C:

“Use a predictive approach with an agreed requirements baseline and formal changes” responds to another technical or business failure: In a fictional CAPM project situation, a public agency has a fixed statutory records format and an approved construction-style deployment specification. That source case depends on: Stable requirements and costly late changes favor more upfront planning and control. The present issue is: In a fictional CAPM project situation, a health network is coordinating a shared electronic-record program containing several interdependent hospital migrations. The more direct action is “Manage the related hospital migrations as a coordinated program rather than unrelated portfolio entries” because a program coordinates related projects to realize benefits unavailable through isolated management.

D:

“Use iterative adaptive delivery with early increments and frequent customer feedback” responds to another technical or business failure: In a fictional CAPM project situation, a startup is prototyping a service whose user journeys change after every customer experiment. That source case depends on: Uncertain solution details benefit from inspection and adaptation rather than a fixed full-scope baseline. The present issue is: In a fictional CAPM project situation, a health network is coordinating a shared electronic-record program containing several interdependent hospital migrations. The more direct action is “Manage the related hospital migrations as a coordinated program rather than unrelated portfolio entries” because a program coordinates related projects to realize benefits unavailable through isolated management.

Question 215

In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. Which underlying project-management principle best explains the appropriate response?

  1. Physical installation without capable operators cannot achieve intended service outcomes.
  2. An identified risk needs a feasible response, not just a label.
  3. Acceptance cannot occur before its required supporting evidence is ready.
  4. Resource availability is a real feasibility constraint for schedule commitments.

Explanation

Correct Answer

C:

The case turns on this distinction: Acceptance cannot occur before its required supporting evidence is ready. Consequently, the targeted action is: Update the dependency network to include mandatory calibration evidence before acceptance. This reasoning can be checked against: The approved schedule shows certificate receipt preceding the formal gate.

Incorrect Answers

A:

“Physical installation without capable operators cannot achieve intended service outcomes” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a new customer service center's opening plan includes equipment deliveries but excludes employee training readiness. There the technical reason is: Physical installation without capable operators cannot achieve intended service outcomes. In this question, the reported issue is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The controlling principle is instead: Acceptance cannot occur before its required supporting evidence is ready.

B:

“An identified risk needs a feasible response, not just a label” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a school software project lists a possible translation delay but never budgets response time for it. There the technical reason is: An identified risk needs a feasible response, not just a label. In this question, the reported issue is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The controlling principle is instead: Acceptance cannot occur before its required supporting evidence is ready.

D:

“Resource availability is a real feasibility constraint for schedule commitments” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. There the technical reason is: Resource availability is a real feasibility constraint for schedule commitments. In this question, the reported issue is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The controlling principle is instead: Acceptance cannot occur before its required supporting evidence is ready.

Question 216

In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Require versioned criteria and advance impact notification.
  2. Maintain a stakeholder communications matrix by requirement impact.
  3. Review response time and stakeholder feedback on the chosen channel.
  4. Measure understanding and update communication plans for affected audiences.

Explanation

Correct Answer

B:

This ongoing practice maintains the improvement: Maintain a stakeholder communications matrix by requirement impact. It follows the targeted action (notify product, operations, compliance, and delivery stakeholders using agreed channels.) and provides a way to catch recurrence. The underlying principle is: Requirements information must reach every role whose work or decision it changes.

Incorrect Answers

A:

“Require versioned criteria and advance impact notification” addresses recurrence of another problem: In a fictional CAPM project situation, a team announces changed acceptance criteria during a release call without telling customer testers in advance. That problem depends on: This ongoing practice maintains the improvement: Require versioned criteria and advance impact notification. The recurring risk here is: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The more targeted safeguard is “Maintain a stakeholder communications matrix by requirement impact” because this ongoing practice maintains the improvement: Maintain a stakeholder communications matrix by requirement impact.

C:

“Review response time and stakeholder feedback on the chosen channel” addresses recurrence of another problem: In a fictional CAPM project situation, a remote engineering team uses lengthy meetings to resolve simple status questions across time zones. That problem depends on: This ongoing practice maintains the improvement: Review response time and stakeholder feedback on the chosen channel. The recurring risk here is: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The more targeted safeguard is “Maintain a stakeholder communications matrix by requirement impact” because this ongoing practice maintains the improvement: Maintain a stakeholder communications matrix by requirement impact.

D:

“Measure understanding and update communication plans for affected audiences” addresses recurrence of another problem: In a fictional CAPM project situation, a multinational employee system announces policy changes through one-language email despite local users with different needs. That problem depends on: This ongoing practice maintains the improvement: Measure understanding and update communication plans for affected audiences. The recurring risk here is: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The more targeted safeguard is “Maintain a stakeholder communications matrix by requirement impact” because this ongoing practice maintains the improvement: Maintain a stakeholder communications matrix by requirement impact.

Question 217

In a fictional CAPM project situation, a rail project collects schedule delays but omits the current approved baseline from status reports. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The status report identifies baseline version, variances, and planned corrections.
  2. Each change has a traceable approval and implementation status.
  3. The performance review includes defect rework forecasts and acceptance status.
  4. The change log shows authorization and revised baselines where approved.

Explanation

Correct Answer

A:

The specified evidence tests the exact improvement at issue: The status report identifies baseline version, variances, and planned corrections. It supports the chosen response (compare actual and earned progress against the current authorized baseline.) rather than merely recording activity. The principle is: Variances are meaningful only relative to an agreed reference point.

Incorrect Answers

B:

“Each change has a traceable approval and implementation status” is evidence for a different source case: In a fictional CAPM project situation, a warehouse expansion has no consistent record of approved site-scope changes. Its related mechanism is: Uncontrolled change history obscures scope and cost accountability. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a rail project collects schedule delays but omits the current approved baseline from status reports. The source-keyed acceptance evidence is “The status report identifies baseline version, variances, and planned corrections”.

C:

“The performance review includes defect rework forecasts and acceptance status” is evidence for a different source case: In a fictional CAPM project situation, an engineering manager reports a favorable cost index but ignores rework due to failed acceptance tests. Its related mechanism is: Cost efficiency alone does not certify delivered scope or required quality. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a rail project collects schedule delays but omits the current approved baseline from status reports. The source-keyed acceptance evidence is “The status report identifies baseline version, variances, and planned corrections”.

D:

“The change log shows authorization and revised baselines where approved” is evidence for a different source case: In a fictional CAPM project situation, a solar installation baseline is revised by email without recording budget and schedule effects. Its related mechanism is: Predictive control depends on authorized changes to reference plans. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a rail project collects schedule delays but omits the current approved baseline from status reports. The source-keyed acceptance evidence is “The status report identifies baseline version, variances, and planned corrections”.

Question 218

In a fictional CAPM project situation, a public agency has a fixed statutory records format and an approved construction-style deployment specification. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Set short feedback intervals and explicit measures for product value.
  2. Review weather triggers regularly and activate the planned contingency when warranted.
  3. Escalate overdue compliance gates and monitor resolution dates.
  4. Review baseline changes through agreed change governance and revalidate compliance.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Review baseline changes through agreed change governance and revalidate compliance. It follows the targeted action (use a predictive approach with an agreed requirements baseline and formal changes.) and provides a way to catch recurrence. The underlying principle is: Stable requirements and costly late changes favor more upfront planning and control.

Incorrect Answers

A:

“Set short feedback intervals and explicit measures for product value” addresses recurrence of another problem: In a fictional CAPM project situation, a startup is prototyping a service whose user journeys change after every customer experiment. That problem depends on: This ongoing practice maintains the improvement: Set short feedback intervals and explicit measures for product value. The recurring risk here is: In a fictional CAPM project situation, a public agency has a fixed statutory records format and an approved construction-style deployment specification. The more targeted safeguard is “Review baseline changes through agreed change governance and revalidate compliance” because this ongoing practice maintains the improvement: Review baseline changes through agreed change governance and revalidate compliance.

B:

“Review weather triggers regularly and activate the planned contingency when warranted” addresses recurrence of another problem: In a fictional CAPM project situation, a bridge team knows seasonal flooding might delay concrete deliveries, but no flooding has occurred. That problem depends on: This ongoing practice maintains the improvement: Review weather triggers regularly and activate the planned contingency when warranted. The recurring risk here is: In a fictional CAPM project situation, a public agency has a fixed statutory records format and an approved construction-style deployment specification. The more targeted safeguard is “Review baseline changes through agreed change governance and revalidate compliance” because this ongoing practice maintains the improvement: Review baseline changes through agreed change governance and revalidate compliance.

C:

“Escalate overdue compliance gates and monitor resolution dates” addresses recurrence of another problem: In a fictional CAPM project situation, a supplier has already missed a required cybersecurity inspection, stopping acceptance today. That problem depends on: This ongoing practice maintains the improvement: Escalate overdue compliance gates and monitor resolution dates. The recurring risk here is: In a fictional CAPM project situation, a public agency has a fixed statutory records format and an approved construction-style deployment specification. The more targeted safeguard is “Review baseline changes through agreed change governance and revalidate compliance” because this ongoing practice maintains the improvement: Review baseline changes through agreed change governance and revalidate compliance.

Question 219

In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. Which underlying project-management principle best explains the appropriate response?

  1. High completion percentages cannot waive specific critical requirements.
  2. A successful demo does not negate a failed mandatory resilience requirement.
  3. Acceptance depends on meeting agreed criteria, not development status alone.
  4. Functional completion cannot replace nonfunctional acceptance evidence.

Explanation

Correct Answer

D:

The case turns on this distinction: Functional completion cannot replace nonfunctional acceptance evidence. Consequently, the targeted action is: Evaluate performance against the nonfunctional acceptance requirement and defer approval if breached. This reasoning can be checked against: Load-test reports show response time under the agreed demand profile.

Incorrect Answers

A:

“High completion percentages cannot waive specific critical requirements” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a public safety dispatch product has traceability for 95% of requirements while five mandatory alerts are untested. There the technical reason is: High completion percentages cannot waive specific critical requirements. In this question, the reported issue is: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The controlling principle is instead: Functional completion cannot replace nonfunctional acceptance evidence.

B:

“A successful demo does not negate a failed mandatory resilience requirement” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. There the technical reason is: A successful demo does not negate a failed mandatory resilience requirement. In this question, the reported issue is: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The controlling principle is instead: Functional completion cannot replace nonfunctional acceptance evidence.

C:

“Acceptance depends on meeting agreed criteria, not development status alone” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a community portal feature is labeled complete although acceptance tests show keyboard-only navigation fails. There the technical reason is: Acceptance depends on meeting agreed criteria, not development status alone. In this question, the reported issue is: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The controlling principle is instead: Functional completion cannot replace nonfunctional acceptance evidence.

Question 220

In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. Which underlying project-management principle best explains the appropriate response?

  1. An SPI below 1 signals that earned value trails scheduled value.
  2. Actual cost exceeds the budgeted value of work performed, indicating overrun.
  3. A CPI above 1 means more budgeted value earned per unit of actual cost.
  4. A WBS organizes the full approved scope by deliverables rather than by random activities.

Explanation

Correct Answer

B:

The case turns on this distinction: Actual cost exceeds the budgeted value of work performed, indicating overrun. Consequently, the targeted action is: Report cost variance CV = EV − AC = −$20,000 and investigate drivers. This reasoning can be checked against: The performance report shows negative $20,000 cost variance.

Incorrect Answers

A:

“An SPI below 1 signals that earned value trails scheduled value” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. There the technical reason is: An SPI below 1 signals that earned value trails scheduled value. In this question, the reported issue is: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. The controlling principle is instead: Actual cost exceeds the budgeted value of work performed, indicating overrun.

C:

“A CPI above 1 means more budgeted value earned per unit of actual cost” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. There the technical reason is: A CPI above 1 means more budgeted value earned per unit of actual cost. In this question, the reported issue is: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. The controlling principle is instead: Actual cost exceeds the budgeted value of work performed, indicating overrun.

D:

“A WBS organizes the full approved scope by deliverables rather than by random activities” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. There the technical reason is: A WBS organizes the full approved scope by deliverables rather than by random activities. In this question, the reported issue is: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. The controlling principle is instead: Actual cost exceeds the budgeted value of work performed, indicating overrun.