Question 190
In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. Which continuing control would most directly reduce the chance of this problem recurring?
Explanation
Correct Answer
This ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes. It follows the targeted action (use a plan-driven approach with detailed design validation before tooling release.) and provides a way to catch recurrence. The underlying principle is: High retooling cost favors early requirements confirmation and formal change control.
Incorrect Answers
“Perform engineering integration reviews before configuration changes” addresses recurrence of another problem: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. That problem depends on: This ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.
“Control baseline amendments through integrated approval and validation” addresses recurrence of another problem: In a fictional CAPM project situation, a regulated laboratory must build equipment to a frozen specification with physical validation gates and costly rework. That problem depends on: This ongoing practice maintains the improvement: Control baseline amendments through integrated approval and validation. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.
“Enforce entry and exit criteria for each planned phase” addresses recurrence of another problem: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. That problem depends on: This ongoing practice maintains the improvement: Enforce entry and exit criteria for each planned phase. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.