Question 170
In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. Which action most directly addresses the problem while respecting the relevant roles and constraints?
Explanation
Correct Answer
This directly addresses the case's governing problem: Calculate CPI = EV / AC = 1.20 and verify the underlying work quality. The key reason is that a CPI above 1 means more budgeted value earned per unit of actual cost. A suitable completion check is: Cost performance index equals 1.20 at the reporting cutoff.
Incorrect Answers
“Decompose the deliverable scope into verifiable WBS work packages” responds to another technical or business failure: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. That source case depends on: A WBS organizes the full approved scope by deliverables rather than by random activities. The present issue is: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. The more direct action is “Calculate CPI = EV / AC = 1.20 and verify the underlying work quality” because a CPI above 1 means more budgeted value earned per unit of actual cost.
“Decompose major deliverables to manageable work packages with accountable owners” responds to another technical or business failure: In a fictional CAPM project situation, a museum exhibit team cannot assign cost accountability because its WBS elements are too broad. That source case depends on: A usable WBS supports planning and cost control at a manageable level. The present issue is: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. The more direct action is “Calculate CPI = EV / AC = 1.20 and verify the underlying work quality” because a CPI above 1 means more budgeted value earned per unit of actual cost.
“Apply the quality plan's inspection and corrective-action procedure before signoff” responds to another technical or business failure: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. That source case depends on: Conformance must be demonstrated against requirements, not presumed from installation. The present issue is: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. The more direct action is “Calculate CPI = EV / AC = 1.20 and verify the underlying work quality” because a CPI above 1 means more budgeted value earned per unit of actual cost.