McAfee Secure

PMI CAPM Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Training Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Training Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 19

Question 180

In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Reserve capacity for refinement and hold frequent product demonstrations.
  2. Define experiment hypotheses and revisit the product goal regularly.
  3. Maintain a prioritized learning backlog and measurable hypotheses.
  4. Agree on team communication norms and demo cadence.

Explanation

Correct Answer

B:

This ongoing practice maintains the improvement: Define experiment hypotheses and revisit the product goal regularly. It follows the targeted action (run short experiments with representative users and adapt priorities from measured outcomes.) and provides a way to catch recurrence. The underlying principle is: Exploratory product uncertainty favors iterative learning over rigid full-detail plans.

Incorrect Answers

A:

“Reserve capacity for refinement and hold frequent product demonstrations” addresses recurrence of another problem: In a fictional CAPM project situation, a travel app team receives weekly consumer feedback that overturns original feature priorities. That problem depends on: This ongoing practice maintains the improvement: Reserve capacity for refinement and hold frequent product demonstrations. The recurring risk here is: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. The more targeted safeguard is “Define experiment hypotheses and revisit the product goal regularly” because this ongoing practice maintains the improvement: Define experiment hypotheses and revisit the product goal regularly.

C:

“Maintain a prioritized learning backlog and measurable hypotheses” addresses recurrence of another problem: In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. That problem depends on: This ongoing practice maintains the improvement: Maintain a prioritized learning backlog and measurable hypotheses. The recurring risk here is: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. The more targeted safeguard is “Define experiment hypotheses and revisit the product goal regularly” because this ongoing practice maintains the improvement: Define experiment hypotheses and revisit the product goal regularly.

D:

“Agree on team communication norms and demo cadence” addresses recurrence of another problem: In a fictional CAPM project situation, a virtual software team lacks a reliable shared board or frequent feedback from its product representative. That problem depends on: This ongoing practice maintains the improvement: Agree on team communication norms and demo cadence. The recurring risk here is: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. The more targeted safeguard is “Define experiment hypotheses and revisit the product goal regularly” because this ongoing practice maintains the improvement: Define experiment hypotheses and revisit the product goal regularly.

Question 181

In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The change record aligns drawings, budget, procurement, schedule, and acceptance.
  2. Network and schedule show test predecessor links and acceptance completion.
  3. Retest results meet the specified pressure threshold with defect closure evidence.
  4. Inspection records show acceptance of each deliverable package.

Explanation

Correct Answer

C:

The specified evidence tests the exact improvement at issue: Retest results meet the specified pressure threshold with defect closure evidence. It supports the chosen response (apply the quality plan's inspection and corrective-action procedure before signoff.) rather than merely recording activity. The principle is: Conformance must be demonstrated against requirements, not presumed from installation.

Incorrect Answers

A:

“The change record aligns drawings, budget, procurement, schedule, and acceptance” is evidence for a different source case: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. Its related mechanism is: Integration management keeps plan components internally consistent. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The source-keyed acceptance evidence is “Retest results meet the specified pressure threshold with defect closure evidence”.

B:

“Network and schedule show test predecessor links and acceptance completion” is evidence for a different source case: In a fictional CAPM project situation, a rail signaling project has three activities dependent on a single final software test, but the test is absent from its network. Its related mechanism is: Omitted dependencies create an artificially early finish forecast. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The source-keyed acceptance evidence is “Retest results meet the specified pressure threshold with defect closure evidence”.

D:

“Inspection records show acceptance of each deliverable package” is evidence for a different source case: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. Its related mechanism is: Estimating work alone does not establish verified completion. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The source-keyed acceptance evidence is “Retest results meet the specified pressure threshold with defect closure evidence”.

Question 182

In a fictional CAPM project situation, a regulator must be informed within two working days of a material incident under the communication plan. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The dashboard agrees with underlying schedule, cost, and risk evidence.
  2. An approved plan defines baseline consumption, target, and measurement period.
  3. A dated notification receipt and incident record demonstrate timely compliance.
  4. Updated requirements and decision records document scope and risk changes.

Explanation

Correct Answer

C:

The specified evidence tests the exact improvement at issue: A dated notification receipt and incident record demonstrate timely compliance. It supports the chosen response (notify the regulator through the approved channel and within the stipulated window.) rather than merely recording activity. The principle is: A communications strategy defines required audiences, timing, and media.

Incorrect Answers

A:

“The dashboard agrees with underlying schedule, cost, and risk evidence” is evidence for a different source case: In a fictional CAPM project situation, a project has a weekly executive dashboard but changes the status color to green to avoid concern. Its related mechanism is: Communication plans do not justify distorting performance information. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a regulator must be informed within two working days of a material incident under the communication plan. The source-keyed acceptance evidence is “A dated notification receipt and incident record demonstrate timely compliance”.

B:

“An approved plan defines baseline consumption, target, and measurement period” is evidence for a different source case: In a fictional CAPM project situation, a campus building project has promised energy savings, but baseline utility consumption was never captured. Its related mechanism is: Benefits realization requires comparing observed outcomes with a valid baseline. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a regulator must be informed within two working days of a material incident under the communication plan. The source-keyed acceptance evidence is “A dated notification receipt and incident record demonstrate timely compliance”.

D:

“Updated requirements and decision records document scope and risk changes” is evidence for a different source case: In a fictional CAPM project situation, a security team receives new data residency requirements after project authorization. Its related mechanism is: New external constraints can alter the project business case and obligations. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a regulator must be informed within two working days of a material incident under the communication plan. The source-keyed acceptance evidence is “A dated notification receipt and incident record demonstrate timely compliance”.

Question 183

In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. What evidence would most directly demonstrate that the appropriate response was effective?

  1. Feedback from tested increments reduces uncertainty about users' real needs.
  2. Working increments and customer observations justify backlog changes.
  3. A visible flow board shows ticket age, throughput, and bounded active work.
  4. Prototype tests reveal which interactions succeed before large commitments.

Explanation

Correct Answer

C:

The specified evidence tests the exact improvement at issue: A visible flow board shows ticket age, throughput, and bounded active work. It supports the chosen response (use an adaptive flow-based approach with explicit priority and work-in-progress limits.) rather than merely recording activity. The principle is: Interrupt-driven work may be managed better through flow than fixed batches.

Incorrect Answers

A:

“Feedback from tested increments reduces uncertainty about users' real needs” is evidence for a different source case: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. Its related mechanism is: Exploratory product uncertainty favors iterative learning over rigid full-detail plans. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. The source-keyed acceptance evidence is “A visible flow board shows ticket age, throughput, and bounded active work”.

B:

“Working increments and customer observations justify backlog changes” is evidence for a different source case: In a fictional CAPM project situation, a travel app team receives weekly consumer feedback that overturns original feature priorities. Its related mechanism is: High product uncertainty benefits from learning through repeated delivery. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. The source-keyed acceptance evidence is “A visible flow board shows ticket age, throughput, and bounded active work”.

D:

“Prototype tests reveal which interactions succeed before large commitments” is evidence for a different source case: In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. Its related mechanism is: Adaptive methods reduce uncertainty through short feedback loops. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. The source-keyed acceptance evidence is “A visible flow board shows ticket age, throughput, and bounded active work”.

Question 184

In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Set the earliest network completion at 15 days along P-Q-S.
  2. Calculate SPI = EV / PV = 63/90 = 0.70 for the reporting period.
  3. Report CV = EV − AC = +$5,000 and verify quality and scope.
  4. Calculate both SV = −$50,000 and CV = −$30,000 before recommending recovery.

Explanation

Correct Answer

A:

This directly addresses the case's governing problem: Set the earliest network completion at 15 days along P-Q-S. The key reason is that the longest dependent route controls completion in an unconstrained network. A suitable completion check is: The long path totals 3+8+4=15 days; the other totals 3+5+4=12.

Incorrect Answers

B:

“Calculate SPI = EV / PV = 63/90 = 0.70 for the reporting period” responds to another technical or business failure: In a fictional CAPM project situation, a campus lighting installation plans 90 days of effort value by the checkpoint but has earned only 63 equivalent days. That source case depends on: Earned work is only 70% of planned work in earned-value terms. The present issue is: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The more direct action is “Set the earliest network completion at 15 days along P-Q-S” because the longest dependent route controls completion in an unconstrained network.

C:

“Report CV = EV − AC = +$5,000 and verify quality and scope” responds to another technical or business failure: In a fictional CAPM project situation, a research laboratory has $55,000 earned value and $50,000 actual cost at the same data date. That source case depends on: The team earned more budgeted value than it spent, absent quality or scope omissions. The present issue is: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The more direct action is “Set the earliest network completion at 15 days along P-Q-S” because the longest dependent route controls completion in an unconstrained network.

D:

“Calculate both SV = −$50,000 and CV = −$30,000 before recommending recovery” responds to another technical or business failure: In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. That source case depends on: The project is behind planned value and over the budgeted cost of work performed. The present issue is: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The more direct action is “Set the earliest network completion at 15 days along P-Q-S” because the longest dependent route controls completion in an unconstrained network.

Question 185

In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. Which underlying project-management principle best explains the appropriate response?

  1. Irreversible hardware interfaces require deliberate baseline control.
  2. Stable external specifications and expensive changes make predictive planning suitable.
  3. High retooling cost favors early requirements confirmation and formal change control.
  4. Predictive work depends on controlled prerequisites to limit expensive downstream changes.

Explanation

Correct Answer

C:

The case turns on this distinction: High retooling cost favors early requirements confirmation and formal change control. Consequently, the targeted action is: Use a plan-driven approach with detailed design validation before tooling release. This reasoning can be checked against: Signed design reviews confirm tolerances prior to manufacturing commitment.

Incorrect Answers

A:

“Irreversible hardware interfaces require deliberate baseline control” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. There the technical reason is: Irreversible hardware interfaces require deliberate baseline control. In this question, the reported issue is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The controlling principle is instead: High retooling cost favors early requirements confirmation and formal change control.

B:

“Stable external specifications and expensive changes make predictive planning suitable” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a regulated laboratory must build equipment to a frozen specification with physical validation gates and costly rework. There the technical reason is: Stable external specifications and expensive changes make predictive planning suitable. In this question, the reported issue is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The controlling principle is instead: High retooling cost favors early requirements confirmation and formal change control.

D:

“Predictive work depends on controlled prerequisites to limit expensive downstream changes” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. There the technical reason is: Predictive work depends on controlled prerequisites to limit expensive downstream changes. In this question, the reported issue is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The controlling principle is instead: High retooling cost favors early requirements confirmation and formal change control.

Question 186

In a fictional CAPM project situation, a service team uses sticky notes but loses information about blocked tickets and work age. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Use transparent product and sprint backlogs with empirical progress forecasts.
  2. Maintain one transparent, accountable product backlog with visible priorities.
  3. Track cycle time consistently in addition to throughput and WIP.
  4. Use a visible flow board that distinguishes blocked work and tracks aging.

Explanation

Correct Answer

D:

This directly addresses the case's governing problem: Use a visible flow board that distinguishes blocked work and tracks aging. The key reason is that adaptive controls rely on transparent work state and feedback. A suitable completion check is: The board and aging data expose bottlenecks before service targets fail.

Incorrect Answers

A:

“Use transparent product and sprint backlogs with empirical progress forecasts” responds to another technical or business failure: In a fictional CAPM project situation, a product team cannot explain why its planned release slipped despite frequent sprints. That source case depends on: Adaptive governance still requires inspectable evidence of scope and progress. The present issue is: In a fictional CAPM project situation, a service team uses sticky notes but loses information about blocked tickets and work age. The more direct action is “Use a visible flow board that distinguishes blocked work and tracks aging” because adaptive controls rely on transparent work state and feedback.

B:

“Maintain one transparent, accountable product backlog with visible priorities” responds to another technical or business failure: In a fictional CAPM project situation, a release coordinator sends a new backlog export daily and teammates cannot identify the current ordered list. That source case depends on: Conflicting unofficial lists erode transparency and alignment. The present issue is: In a fictional CAPM project situation, a service team uses sticky notes but loses information about blocked tickets and work age. The more direct action is “Use a visible flow board that distinguishes blocked work and tracks aging” because adaptive controls rely on transparent work state and feedback.

C:

“Track cycle time consistently in addition to throughput and WIP” responds to another technical or business failure: In a fictional CAPM project situation, a Kanban support team records throughput but does not capture the time taken from work start to finish. That source case depends on: Flow health needs elapsed-time evidence, not only quantity finished. The present issue is: In a fictional CAPM project situation, a service team uses sticky notes but loses information about blocked tickets and work age. The more direct action is “Use a visible flow board that distinguishes blocked work and tracks aging” because adaptive controls rely on transparent work state and feedback.

Question 187

In a fictional CAPM project situation, a public payment portal team collects only internal views and ignores external taxpayers. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Include representative external users in discovery and validation.
  2. Clarify strategic process ownership separately from day-to-day process management.
  3. Define product decision rights for feature value and project governance for delivery commitments.
  4. Have the process owner approve exception rules while IT translates them into system behavior.

Explanation

Correct Answer

A:

This directly addresses the case's governing problem: Include representative external users in discovery and validation. The key reason is that external actors can determine success even when they are outside the organization. A suitable completion check is: The requirements record separates taxpayer needs from internal administrative needs.

Incorrect Answers

B:

“Clarify strategic process ownership separately from day-to-day process management” responds to another technical or business failure: In a fictional CAPM project situation, a hospital claims department has a process owner responsible for outcomes and a supervisor managing daily staff activity. That source case depends on: Process owners govern outcomes; process managers coordinate ongoing execution. The present issue is: In a fictional CAPM project situation, a public payment portal team collects only internal views and ignores external taxpayers. The more direct action is “Include representative external users in discovery and validation” because external actors can determine success even when they are outside the organization.

C:

“Define product decision rights for feature value and project governance for delivery commitments” responds to another technical or business failure: In a fictional CAPM project situation, a product manager and project manager both believe they alone approve feature priority and delivery dates. That source case depends on: Product and project accountabilities overlap but are not identical. The present issue is: In a fictional CAPM project situation, a public payment portal team collects only internal views and ignores external taxpayers. The more direct action is “Include representative external users in discovery and validation” because external actors can determine success even when they are outside the organization.

D:

“Have the process owner approve exception rules while IT translates them into system behavior” responds to another technical or business failure: In a fictional CAPM project situation, an insurance claims modernization team asks the IT lead to define business exceptions without consulting the actual claims process owner. That source case depends on: IT delivery expertise does not replace business-policy accountability. The present issue is: In a fictional CAPM project situation, a public payment portal team collects only internal views and ignores external taxpayers. The more direct action is “Include representative external users in discovery and validation” because external actors can determine success even when they are outside the organization.

Question 188

In a fictional CAPM project situation, a consultant evaluating bids for a city project discovers a relative owns one bidding firm. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Disclose the conflict and recuse or follow the required impartial procurement process.
  2. Report the verified adverse results accurately through authorized channels.
  3. Assess the proposed mobile app against objectives and route any scope expansion for approval.
  4. Record the intended waiting-time benefit and how it will be measured after delivery.

Explanation

Correct Answer

A:

This directly addresses the case's governing problem: Disclose the conflict and recuse or follow the required impartial procurement process. The key reason is that undisclosed personal interest compromises fairness and the appearance of impartiality. A suitable completion check is: The conflict disclosure and independent evaluation record show fair treatment of bidders.

Incorrect Answers

B:

“Report the verified adverse results accurately through authorized channels” responds to another technical or business failure: In a fictional CAPM project situation, a project sponsor urges the coordinator to hide adverse test results before a regulator briefing. That source case depends on: Professional honesty forbids knowingly misleading stakeholders about material results. The present issue is: In a fictional CAPM project situation, a consultant evaluating bids for a city project discovers a relative owns one bidding firm. The more direct action is “Disclose the conflict and recuse or follow the required impartial procurement process” because undisclosed personal interest compromises fairness and the appearance of impartiality.

C:

“Assess the proposed mobile app against objectives and route any scope expansion for approval” responds to another technical or business failure: In a fictional CAPM project situation, a team proposes adding a mobile app to a water-meter project whose approved scope covers only sensor installation. That source case depends on: An attractive feature is not automatically within the authorized project scope. The present issue is: In a fictional CAPM project situation, a consultant evaluating bids for a city project discovers a relative owns one bidding firm. The more direct action is “Disclose the conflict and recuse or follow the required impartial procurement process” because undisclosed personal interest compromises fairness and the appearance of impartiality.

D:

“Record the intended waiting-time benefit and how it will be measured after delivery” responds to another technical or business failure: In a fictional CAPM project situation, a hospital redesign aims to shorten patient waiting time but its charter only mentions installing kiosks. That source case depends on: Delivering kiosks is an output; shorter waits are an outcome requiring validation. The present issue is: In a fictional CAPM project situation, a consultant evaluating bids for a city project discovers a relative owns one bidding firm. The more direct action is “Disclose the conflict and recuse or follow the required impartial procurement process” because undisclosed personal interest compromises fairness and the appearance of impartiality.

Question 189

In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. Which underlying project-management principle best explains the appropriate response?

  1. Adaptive planning emphasizes small, coherent increments of user value.
  2. Adaptive progress is better evidenced through usable value than unvalidated activity percentages.
  3. Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus.
  4. A prioritized item is not automatically feasible within the current iteration.

Explanation

Correct Answer

A:

The case turns on this distinction: Adaptive planning emphasizes small, coherent increments of user value. Consequently, the targeted action is: Slice the deliverable into independently demonstrable user outcomes with acceptance criteria. This reasoning can be checked against: The sprint delivers a testable increment rather than disconnected technical tasks.

Incorrect Answers

B:

“Adaptive progress is better evidenced through usable value than unvalidated activity percentages” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a team uses the percentage of a fixed annual scope completed as the only indicator of adaptive progress. There the technical reason is: Adaptive progress is better evidenced through usable value than unvalidated activity percentages. In this question, the reported issue is: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. The controlling principle is instead: Adaptive planning emphasizes small, coherent increments of user value.

C:

“Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a product owner announces a new urgent feature mid-sprint and demands that the Sprint Goal stay unchanged without discussion. There the technical reason is: Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus. In this question, the reported issue is: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. The controlling principle is instead: Adaptive planning emphasizes small, coherent increments of user value.

D:

“A prioritized item is not automatically feasible within the current iteration” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a team selects a high-priority story requiring a vendor interface that will not ship until the following month. There the technical reason is: A prioritized item is not automatically feasible within the current iteration. In this question, the reported issue is: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. The controlling principle is instead: Adaptive planning emphasizes small, coherent increments of user value.

Question 190

In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Perform engineering integration reviews before configuration changes.
  2. Control baseline amendments through integrated approval and validation.
  3. Enforce entry and exit criteria for each planned phase.
  4. Require engineering-change review for postrelease tolerance changes.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes. It follows the targeted action (use a plan-driven approach with detailed design validation before tooling release.) and provides a way to catch recurrence. The underlying principle is: High retooling cost favors early requirements confirmation and formal change control.

Incorrect Answers

A:

“Perform engineering integration reviews before configuration changes” addresses recurrence of another problem: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. That problem depends on: This ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.

B:

“Control baseline amendments through integrated approval and validation” addresses recurrence of another problem: In a fictional CAPM project situation, a regulated laboratory must build equipment to a frozen specification with physical validation gates and costly rework. That problem depends on: This ongoing practice maintains the improvement: Control baseline amendments through integrated approval and validation. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.

C:

“Enforce entry and exit criteria for each planned phase” addresses recurrence of another problem: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. That problem depends on: This ongoing practice maintains the improvement: Enforce entry and exit criteria for each planned phase. The recurring risk here is: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. The more targeted safeguard is “Require engineering-change review for postrelease tolerance changes” because this ongoing practice maintains the improvement: Require engineering-change review for postrelease tolerance changes.