Question 200
In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: Scrum Master accountability is team effectiveness, not ownership of product value order. Consequently, the targeted action is: Restore product-backlog ordering decisions to the product owner, with Scrum Master facilitation. This reasoning can be checked against: Backlog change decisions have clear product ownership and transparent rationale.
Incorrect Answers
“The Sprint Review is a working session to inspect outcomes and adapt plans” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum team turns the Sprint Review into a manager's status presentation without product feedback. There the technical reason is: The Sprint Review is a working session to inspect outcomes and adapt plans. In this question, the reported issue is: In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. The controlling principle is instead: Scrum Master accountability is team effectiveness, not ownership of product value order.
“The retrospective examines team effectiveness rather than proving product acceptance” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. There the technical reason is: The retrospective examines team effectiveness rather than proving product acceptance. In this question, the reported issue is: In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. The controlling principle is instead: Scrum Master accountability is team effectiveness, not ownership of product value order.
“Excess WIP increases context switching and queues” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. There the technical reason is: Excess WIP increases context switching and queues. In this question, the reported issue is: In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. The controlling principle is instead: Scrum Master accountability is team effectiveness, not ownership of product value order.