Question 360
A bridge refurbishment project completes component inspections without a stable inventory linking installed components to product descriptions. Which recurring review would keep this control effective as the project changes?
Explanation
Correct Answer
Use version control and review product status at delivery milestones to prevent outdated components from being mistaken for accepted products. It is appropriate because quality assurance depends on knowing which product version was tested and approved, not merely having a signed report with no configuration reference. The recurring failure risk is illustrated by: A bridge refurbishment project completes component inspections without a stable inventory linking installed components to product descriptions.
Incorrect Answers
This repeating check is mainly concerned with use a risk budget for uncertainty, not with the recurring weakness described here: A bridge refurbishment project completes component inspections without a stable inventory linking installed components to product descriptions. The useful ongoing safeguard in this situation is to use version control and review product status at delivery milestones to prevent outdated components from being mistaken for accepted products.
This repeating check is mainly concerned with distinguish quality planning from control, not with the recurring weakness described here: A bridge refurbishment project completes component inspections without a stable inventory linking installed components to product descriptions. The useful ongoing safeguard in this situation is to use version control and review product status at delivery milestones to prevent outdated components from being mistaken for accepted products.
This repeating check is mainly concerned with project manager versus project board authority, not with the recurring weakness described here: A bridge refurbishment project completes component inspections without a stable inventory linking installed components to product descriptions. The useful ongoing safeguard in this situation is to use version control and review product status at delivery milestones to prevent outdated components from being mistaken for accepted products.