Question 380
A supplier sends an independent audit certificate and assumes it automatically proves that the specific delivered service meets every customer quality criterion. What repeating management check should be included in the project controls?
Explanation
Correct Answer
Review how quality assurance findings feed into corrective tests and acceptance decisions without confusing the responsibilities. It is appropriate because a healthy quality management process does not by itself demonstrate a particular product passed its agreed criteria or was accepted by the user. The recurring failure risk is illustrated by: A supplier sends an independent audit certificate and assumes it automatically proves that the specific delivered service meets every customer quality criterion.
Incorrect Answers
This repeating check is mainly concerned with maintain the quality register, not with the recurring weakness described here: A supplier sends an independent audit certificate and assumes it automatically proves that the specific delivered service meets every customer quality criterion. The useful ongoing safeguard in this situation is to review how quality assurance findings feed into corrective tests and acceptance decisions without confusing the responsibilities.
This repeating check is mainly concerned with ensure independent review of a critical output, not with the recurring weakness described here: A supplier sends an independent audit certificate and assumes it automatically proves that the specific delivered service meets every customer quality criterion. The useful ongoing safeguard in this situation is to review how quality assurance findings feed into corrective tests and acceptance decisions without confusing the responsibilities.
This repeating check is mainly concerned with agree measurable acceptance criteria, not with the recurring weakness described here: A supplier sends an independent audit certificate and assumes it automatically proves that the specific delivered service meets every customer quality criterion. The useful ongoing safeguard in this situation is to review how quality assurance findings feed into corrective tests and acceptance decisions without confusing the responsibilities.