Question 370
A building safety sensor fails the agreed accuracy threshold, but the team wants to record completion because remediation is inconvenient. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that a product cannot be considered conforming merely because schedule pressure exists; any permitted acceptance of a deviation needs explicit authority. That reasoning makes the targeted action appropriate: treat failed criteria as defects requiring controlled correction, approved concession where permitted, or escalation before acceptance. The described project conditions show why the distinction matters: A building safety sensor fails the agreed accuracy threshold, but the team wants to record completion because remediation is inconvenient.
Incorrect Answers
Product register and configuration identification describes a different management issue. The relevant cause instead is that a product cannot be considered conforming merely because schedule pressure exists; any permitted acceptance of a deviation needs explicit authority.
Separate assurance, control and acceptance describes a different management issue. The relevant cause instead is that a product cannot be considered conforming merely because schedule pressure exists; any permitted acceptance of a deviation needs explicit authority.
Distinguish quality planning from control describes a different management issue. The relevant cause instead is that a product cannot be considered conforming merely because schedule pressure exists; any permitted acceptance of a deviation needs explicit authority.